Welcome to our Firehouse Construction Update Page

"In Honor of those who served before us... 
In hope of those who will serve after us..."

Live Construction Video Feed:

Currently working on: Roof Installation and Utility Installation

Next Up: Concrete pour for 1st floor

 

Some Basic Details:

  • Vacated old station: February 16, 2020
  • Demolition of the Old Station: April 3, 2020
  • Anticipated Completion Date: Spring 2021
  • Number of Bays: 5, 4 for Mt. Tabor FD and 1 for Par-Troy EMS
  • Budget: $5.2 million